Project Overview
At the end of July, PT Ferro started excavating for what would be their first ever StormTrap Installation. The StormTrap system was designed to hold up to 27,244.50 Cubic Feet of storm water, was 10’ tall, and required an excavation depth of 15’. Approximately 4,000 CY of earth was excavated in 2 days. Following the installation of the StormTrap, PT Ferro continued with additional storm drainage, aggregate base course, concrete curb, concrete sidewalk & driveway aprons, and finished placing the asphalt pavement by the end of september, less than 2 months after starting the project.
University of St. Francis – Underground Detention System
- University of St. Francis
- Joliet, IL
- September, 2018